Process improvement

Five steps: baseline the floor from video, trace lost time to its root cause, propose ranked changes, quantify each one, and track adoption and impact as the measures keep updating.

A fabrication line with six stations along a roller conveyor. Blue boxes mark the units being tracked at each station, and the floor along the conveyor glows blue, turning amber where units queue before fit-up.

Step 1 of 5

Baseline

Video from the floor, joined to existing plant data such as MES and ERP records, is converted into measures for each station.

Time use by station

Share of shift, ten shifts pooled

  • Working on the product
  • Setup and handling
  • Waiting
  • Walking
  • Breaks, or nobody there
Fit-up Station A
39%
29%
13%
13%
Weld Booth 3
18%
38%
17%
11%
16%
Weld Booth 5
26%
37%
14%
9%
14%
SAW long seam
31%
36%
12%
15%
Time use by station, percent of shift
StationWorking on the productSetup and handlingWaitingWalkingBreaks, or nobody there
Fit-up Station A39%29%13%6%13%
Weld Booth 318%38%17%11%16%
Weld Booth 526%37%14%9%14%
SAW long seam31%36%12%6%15%
Time use
The share of the shift spent on value-added work (the work that changes the part), on support such as setup and handling, and on waiting or walking.
Utilization
The share of the shift in which a station has both work and a person at it.
Cycle time
How long one unit spends at a station, and how much that varies.
Throughput
Units finished per day, against plan.
Rework
Time spent redoing work already done.
Shift profile
How activity rises and falls across the day, including the breaks.

Set up in a week. Results in week two.