Case studiesRidgeline Container Works · Sample report
Operational baseline
Four-camera observation of fit-up and welding over ten shifts, joined to traveler, quality and scheduling data. Prepared for the president and the VP of operations.
- 50 days
- Median lead time
- 43 hours
- Worked on per canister
- 3.3 / week
- Canisters finished
1. What we found
Ridgeline's canisters spend 50 days on the floor for 43 hours of work. The constraint is fit-up, not welding. The welders wait on the fitters for about a tenth of the shift, and the manual booths have the arc lit 18 to 26 percent of the time. Five changes that need no capital raise throughput from 3.3 to about 4.5 canisters a week.
- Flow. A canister is being worked on 3.6 percent of the time it is in the building. Of the 50-day lead time, 37 days are queue, and the two largest queues are both in front of fit-up.
- Constraint. Fit-up is loaded at 105 percent of its available hours. Fit-up Station A is hands-on for 68 percent of the shift. The rest is crane waits, inspector waits and walking, so the constraint is under-used before it needs more capacity.
- Welding. Shift start, shift end and the minutes after each break account for much of the gap between the booths and a well-run manual station.
- Method. The same circ seam takes a median of 45 minutes by the fastest observed method and 68 by the slowest. The quality of the fit-up received moves the median from 42 to 60 minutes.
- Layout. A canister takes 13 crane lifts and about 1,100 feet of travel. Welders walk to the consumables crib about 24 times a shift.
- Automation. On today's numbers, automating welding without relieving fit-up adds no throughput.
2. Data and method
The analysis joins three kinds of data: what the cameras saw, what the travelers and the ERP recorded, and what the quality system logged. Each minute of video at each station was classified into an activity, and the activities roll up into five categories: value-added work, support work, waiting, walking, and breaks and idle.
- Activity classification
- Coverage4 cameras, per minute, 10 shifts
- SourceCobalt video pipeline
- Traveler events
- Coverage24 canisters × 10 operations
- SourceERP job costing and sign-offs
- Per-joint weld cycles
- Coverage141 observed joints
- SourceCamera events and traveler joint IDs
- Load against capacity
- Coverage9 work centers, next 8 weeks
- SourceERP scheduling and headcount
- Daily work in process
- Coverage9 locations × 10 days
- SourceCamera count and floor walk
- Nonconformance log
- Coverage12 months
- SourceQuality system
| Dataset | Coverage | Source |
|---|---|---|
| Activity classification | 4 cameras, per minute, 10 shifts | Cobalt video pipeline |
| Traveler events | 24 canisters × 10 operations | ERP job costing and sign-offs |
| Per-joint weld cycles | 141 observed joints | Camera events and traveler joint IDs |
| Load against capacity | 9 work centers, next 8 weeks | ERP scheduling and headcount |
| Daily work in process | 9 locations × 10 days | Camera count and floor walk |
| Nonconformance log | 12 months | Quality system |
Before the classification was used, it was checked class by class against an industrial engineer who coded a sample of the footage independently. Grinding as preparation and grinding as rework are the hardest to tell apart, so rework figures are quoted as a range and were spot-checked against traveler joint IDs.
3. Current state: how a canister flows
The value stream map is the one-page picture of the plant. The boxes are the operations on a canister's traveler, the triangles are canisters waiting between them, and the two rungs underneath split the time into waiting and being worked on. The two highlighted boxes are the same work center, fit-up, and the largest triangles sit in front of them. The arithmetic checks: 23 open canisters at 3.3 a week is about 49 days, which is the measured lead time.
Current-state value stream map
One canister family. Median queue before each step, and hours worked at it.
- 2.0 dCut and form3 h
- 1.5 dRoll2 h
- 2.5 dLong seam4 h
- 7.0 dFit-up: heads6 h
- 3.0 dCirc seams9 h
- 8.5 dFit-up: nozzles5 h
- 2.5 dNozzle welds7 h
- 5.0 dRadiography2 h
- 2.5 dPressure test2 h
- 2.5 dFinish3 h
- Lead time
- 50 days
- Queued
- 37 days
- Worked on
- 43 hours
- Share of lead time worked on
- 3.6%
4. The constraint
Three independent signals point to fit-up. The floor count shows where canisters pile up. The ERP load shows which work center has more scheduled hours than it has people. The cameras at the weld booths show welders standing in an empty booth waiting for a fitted assembly.
Load by station
Scheduled hours as a share of available hours. Under each bar, the units queued in front of that station.
Bottleneck: Fit-up. It is loaded above its available hours and has the deepest queue.
Roughly a fifth of the constraint's day is waiting or walking. An hour recovered at fit-up is an hour of plant throughput. The same hour recovered at the long seam station is worth nothing today. This ordering drives the ranking in section 7.
Idle by cause
Fit-up Station A, minutes per shift
5. What each station is doing
The time-use chart is the camera equivalent of a classic work sampling study, with about 4,600 observations per station in place of a few hundred.
Time use by station
Share of shift, ten shifts pooled
- Value-added work
- Support work
- Waiting
- Walking
- Breaks and idle
| Station | Value-added work | Support work | Waiting | Walking | Breaks and idle |
|---|---|---|---|---|---|
| Fit-up Station A | 39% | 29% | 13% | 6% | 13% |
| Weld Booth 3 | 18% | 38% | 17% | 11% | 16% |
| Weld Booth 5 | 26% | 37% | 14% | 9% | 14% |
| SAW long seam | 31% | 36% | 12% | 6% | 15% |
Shift profile
Share of covered stations with hands-on work under way, by half hour
| Time | Hands-on |
|---|---|
| 06:30 | 31% |
| 07:00 | 58% |
| 07:30 | 71% |
| 08:00 | 74% |
| 08:30 | 72% |
| 09:00 | 38% |
| 09:30 | 61% |
| 10:00 | 73% |
| 10:30 | 75% |
| 11:00 | 69% |
| 11:30 | 22% |
| 12:00 | 49% |
| 12:30 | 68% |
| 13:00 | 70% |
| 13:30 | 41% |
| 14:00 | 57% |
| 14:30 | 29% |
The losses that are easiest to recover, at shift start, after breaks, walking to the crib and waiting for consumables, are not welding problems. They are staging problems, and one material handler solves most of them.
6. Method variation and standard work
Differences in method between stations are stable from day to day, which means they can be standardized. Standard work is not a quality procedure: the weld specification already governs amps, volts and travel speed. It is the sequence and staging of the fastest, cleanest observed method, written down so that every station can use it.
Standard work: fit up and tack, head to shell
Best-observed method, Fit-up Station A. Reviewed with the station's leads.
- Steps
- 6
- Standard time
- 41 min
- Revision
- A
- Step 13 min
Confirm the drawing revision and weld map
Stop if the revision does not match the traveler.
- Step 26 min
Stage the shell, head and tack consumables
Staged by the material handler before the shift, not by the fitter.
- Step 38 min
Set the shell on the rollers and level it
Level before the head is lifted. Re-levelling under the crane holds the crane.
- Step 412 min
Align the head and check the gap
A gap over 1/8 in goes back to forming. It is not welded up.
- Step 59 min
Tack at four points in opposite pairs
Re-check the gap after the second tack.
- Step 63 min
Sign the traveler and call the hold point
Call the inspector now, so the booth is not left waiting.
7. Changes, ranked by throughput
The ranking follows the constraint. Anything that recovers fit-up hours, or keeps a poor fit-up out of the booths, comes first.
Ranked changes
Estimated value in canisters per week
- 1+0.4 / week
Stage kits and consumables with one material handler
Fit-up, weld booths
Cam 1 · 07:12Cam 3 · 09:41 - 2+0.3 / week
Book the hold-point inspector when fit-up starts, not when welding ends
Fit-up
Cam 1 · 10:26 - 3+0.2 / week
Check the fit-up gap before the assembly leaves the station
Fit-up
Cam 1 · 13:05Cam 4 · 13:48 - 4+0.2 / week
Adopt the best-observed circ seam sequence at all four booths
Weld booths
Cam 3 · 08:15Cam 4 · 08:22 - 5+0.1 / week
Stage the first job of the shift the afternoon before
All stations
Cam 2 · 06:34
Throughput model
With changes 1 to 5
Load: scheduled hours as a share of available hours.
- Throughput
- 4.5canisters per week+36% against baseline
- Constraint
- NDElimits the whole lineMoves from Fit-up
- Cost per unit
- $17,900labor and overhead-16% against baseline
Two cautions. The effects are only approximately additive: once fit-up is relieved the constraint moves, most likely to the radiography windows, and the ranking should be redone at that point. And the first change assumes a helper can be reassigned. If not, that role is the first hire to make, ahead of any welding automation.
8. Baseline for judging welding automation
A robotic cell judged against today's average will look better than it is. It should be judged against the best-observed manual cycle, at the same inspection method, with rework and setup counted on both sides, and only once fit-up is confirmed as no longer the constraint.
- Arc time as a share of the shift
- Current baseline18% and 26%, manual booths
- How it is measuredContinuous, per station
- Cycle time per circ seam
- Current baseline45 to 68 min, by method
- How it is measuredPer joint, timestamped
- First-pass yield at radiography
- Current baseline84%
- How it is measuredWeekly, from the NDE vendor
- Rework per canister, observed
- Current baseline4.5 hours
- How it is measuredCamera: grind-out and re-weld
- Setup per canister at the booth
- Current baseline38 min, median
- How it is measuredCamera: last cap to first arc
- Canisters finished per week
- Current baseline3.3
- How it is measuredERP completions
| Measure | Current baseline | How it is measured |
|---|---|---|
| Arc time as a share of the shift | 18% and 26%, manual booths | Continuous, per station |
| Cycle time per circ seam | 45 to 68 min, by method | Per joint, timestamped |
| First-pass yield at radiography | 84% | Weekly, from the NDE vendor |
| Rework per canister, observed | 4.5 hours | Camera: grind-out and re-weld |
| Setup per canister at the booth | 38 min, median | Camera: last cap to first arc |
| Canisters finished per week | 3.3 | ERP completions |
The same cameras stay in place. A robotic cell would get a camera of its own, with the same activity classes and two more for programming and fixture loading, and the comparison would run over twenty shifts on the same product mix.
Assumptions and limits
- One shift was observed. Second-shift behaviour is unmeasured.
- Cameras covered one of two fit-up stations and two of four booths. Station-level figures are extrapolated to the unobserved stations for the throughput model.
- Hours worked come from job costing, which operators book at the end of the day and round. Elapsed camera time was used wherever the two disagreed.
See it on your own floor
This is the report for a fictional plant. Get in touch to talk about one for yours.